03-2014 Power substation elements

From 27thMarch to 3rdApril,
MULLER Dordrecht, in cooperation with Rhenus Logistics France, performed a very delicate and impressive rolling operations at STX St Nazaire yard.

The cargo was a power substation built by STX France for the account of the Danish Energy Company DONG Energy. It consisted of a topside (Dimensions 32 x 25 x 25 m – 1600 Tons), stacks (lenght 54 m – 985 tons) and jacket (Dimensions 32 x 32 x 41 m – 1360 Tons).

The substation elements loaded on MULLER’s barge were subsequently towed and installed in the Westermost Rough wind farm situated off the South-East coast of England.

 